Timeline
Sep 2019: New facility at 256 Grays Inn Road receives conditional planning permission,Ìýand theÌýEastman Dental Hospital closesÌýin October 2019
FebÌý2020: 256 Grays Inn Road site vacated and enabling work begins. The new Eastman Dental Hospital on Huntley StreetÌýis formally opened by the QueenÌý
May 2020: Camden Council grants full planning permission following approval from Greater London Authority
JulÌý2020: Contract awarded to ISG as the main contractor
May 2021: Ground breaking marks start of demolition
Q3 2021: Piling and groundworks begin
Q4 2021: Substructure work begins
Q3 2022: Superstructure and external works begin
Q4 2022: Building fit-out begins
May 2024: Building operational and IoN, UK DRI and NHNN move in